Programme Plan

The section provides details of the overall programme phases and latest timescales.

The bilateral transactions programme is being delivered in three phases:

1. Initiation (January – end May 2020) - COMPLETED
Including all activity required to reach approval of the Outline Business Case.

2. Planning (June – end September 2020) - COMPLETED
All activity required to reach approval of the Full Business Case and to progress to execution

3. Execution (October 2020 onwards) - UNDERWAY
All activity required to complete implementation of the solution, up to and including the close-down of the programme at the end of November 2022 (see below)

Bilaterals POAP april 2022

The high level programme plan for Phases 2 to 6, which is mandated by the Authority Change Proposal CPW070, is shown below. 

The Bilateral Transactions Programme is being delivered in three phases:

1. Initiation (January – end May 2020) - COMPLETED
Including all activity required to reach approval of the Outline Business Case.

2. Planning (June – end September 2020) - COMPLETED
All activity required to reach approval of the Full Business Case and to progress to execution

3. Execution (October 2020 onwards) - UNDERWAY
All activity required to complete implementation of the solution, up to and including the close-down of the programme.