Performance Rectification Plans

A Performance Rectification Plan (PRP) is issued to a trading party who has failed to meet acceptable levels of performance and as such, this issue is escalated to the Performance Assurance Committee (PAC) for further involvement. At this point, the PRP is agreed with the PAC and the trading party with an approach on improving their performance levels in a particular area.

You can find out more about the process of escalating trading parties due to performance concerns in Code Subsidiary Document CSD0002 (Section 7.6). Our Performance Resolution Policy (Section 4) describes our approach to publishing this information on our website.

Active Plans

Trading Party PRP Start Date Plan Status Duration Performance Standard

Yu Water

June 2025

Plan requested

-

Holistic Performance Measures - MPS and Long Unread Meters

South Staffordshire Water

January 2025

Plan accepted

Open ended

Holistic Performance Measures - OPS Metering & Verification, OPS Customer Service & Disconnection, MPS, UPRN, VOA, Long Term Vacancy and Legacy Long Unread Meters